How many machines do I need?

How many machines you need comes from dividing the work (area × lifts × passes) by what one unit does per day, and comparing that with your deadline. Enter area, depth and days in the calculator: it uses each SIMAQ compactor's width, working speed and passes — from the SQ15 PRO plate to the rollers — and tells you how many units hit the date.

A spec sheet tells you weight and force. It never tells you the one thing that decides the purchase: whether it gets you to the deadline.

01

Width isn't width

Passes must overlap or you leave an uncompacted strip between them, exactly where nobody looks. That overlap eats about 10% of plate or drum width: usable width is always less than the catalogue figure.

02

Passes divide

A machine needing six passes produces half as much as one needing three, even at the same width. That's why the right machine for the soil beats the big machine: passes divide output directly.

03

Working speed

Catalogues publish top speed, which is for travelling, not compacting. Real compaction is slow: using the maximum inflates output two or threefold, and that's the error that makes a job planned on paper finish late.

04

Lift thickness sets the laps

Total depth isn't compacted in one go. Each machine densifies to a certain depth, and a thicker lift leaves the bottom loose even when the surface looks firm. A machine that bites thicker lifts makes fewer laps — worth as much as its width.

SIMAQ rollers by width and weight

More drum = more metres per pass; more weight = thicker lifts. Place your job before running the numbers.

SIMAQ rollers by tonnage, drum width and useHorizontal bar chart with the tonnage of each SIMAQ roller, grouped by typical use. Patching, sidewalks and access: SQRDWB L34, walk-behind, 0.84 tonnes, 680 millimeter drum; SQRD L41, ride-on, 0.8 tonnes, 700 millimeter drum. Trench: SQRDPWB L102, padfoot, 0.78 tonnes, 680 millimeter drum; SQRPTRC L202, remote control, 1.53 tonnes, 600 or 850 millimeter drum. Subdivisions and streets: SQRD L51, ride-on, 1.5 tonnes, 900 millimeter drum. Roadway and embankment: SQRD L61, ride-on, 3 tonnes, 1200 millimeter drum; SQRD L71, ride-on and diesel, 4.2 tonnes.1 t2 t3 t4 tPatching, sidewalks, accessSQRDWB L34 · walk-behind0.84 t · 680 mmSQRD L41 · ride-on0.8 t · 700 mmTrenchSQRDPWB L102 · padfoot0.78 t · 680 mmSQRPTRC L202 · remote control1.53 t · 600/850 mmSubdivisions and streetsSQRD L51 · ride-on1.5 t · 900 mmRoadway and embankmentSQRD L61 · ride-on3 t · 1200 mmSQRD L71 · ride-on, diesel4.2 t
Tonnes and drum width from each model's spec sheet. More tonnage, thicker lifts and more ground per pass.

Run your job

Enter your real job size and the deadline you have. The calculation uses each SIMAQ machine's width, speed and passes to tell you how many units it takes to hit the date.

Soil type

2,000 m² at 40 cm, in 10 days of 8 h. How many lifts it takes depends on the machine — see the table.

MachineOutputPassesLiftsWith 1 unitTo hit the date
SQRD L71Ride-on roller 4.2 t · estimated1,126 m²/h424 h1
SQRD L61Ride-on roller 3 t · estimated780 m²/h425 h1
SQRD L51Ride-on roller 1.5 t · estimated504 m²/h428 h1
SQRD L41Ride-on roller 0.8 t · estimated329 m²/h432.3 days1
SQRDPWB L102Padfoot (trench) · estimated320 m²/h432.3 days1
SQRDWB L34Walk-behind tandem · estimated320 m²/h432.3 days1
SQRPTRC L202Padfoot (trench) · estimated286 m²/h432.6 days1
SQ15 PROVibratory plate143 m²/h423.5 days1
SQ60 PRO 2Rammer · estimated76 m²/h339.9 days1

Output = usable width × working speed × 50 productive minutes per hour ÷ passes. Usable width deducts 10% overlap (without it you leave an uncompacted strip between passes) and compacted thickness deducts 20% settlement from the loose lift. Working speed is NOT the catalogue top speed: real compaction requires moving slowly, and using the maximum would inflate output two or threefold. This is a planning estimate — a test strip in your own material overrules any table.

The cheap machine can cost more

Halve the deadline and watch the last column. A narrow machine that looked sufficient now needs two or three units — and operators, fuel, transport and maintenance multiply with them. The real comparison between two machines is never price against price: it's how many units and how many days against the delivery date.

And the flip side: in a trench or confined space the big roller doesn't fit, and there the narrow machine isn't the cheap option — it's the only one. That's what the compaction lesson is for: it starts from the soil, not the date.

FAQ

What people ask most

How many machines do I need to compact my job?

Divide the total work (area × number of lifts) by what one machine does per day and compare it with the days you have. This lesson's calculator does it with each SIMAQ compactor's width, working speed and passes.

How do you calculate a compactor's output?

Output = usable width × working speed × productive minutes per hour ÷ passes. Usable width deducts about 10% overlap between strips, and speed is compacting speed, not the spec sheet maximum.

Can I use the spec sheet top speed for planning?

No. Top speed is for travelling; real compaction is slow, and using the catalogue maximum inflates output two or threefold. It's the mistake that makes a job planned on paper finish late.

What happens if my deadline is cut in half?

If the deadline halves, you need twice the units — and operators, fuel, transport and maintenance multiply with them. That's why you compare units and days against the date, not price against price.

Is one big machine better than several small ones?

On open ground, a wider machine that needs fewer passes usually outperforms several narrow ones. In a trench or confined space the big roller won't fit: there the SQRDPWB L102 trench roller or the SQ60 PRO 2 rammer is the only option.

Get a quote without leaving

Want to work it out with an advisor?

Topic: Equipment for my project

Get advice and a quote

Leave your name and phone: a specialist in your country will text or call you.

Your country*
A specialist contacts you during business hours (Mon–Fri 8:00–17:00 / Sat 8:00–12:00).

Ready for a quote?

Tell us about the job and we'll build the package. A rep replies during business hours.

WhatsAppGet a quote